Quantity Surveying Glossary – 25 Key Terms Explained
This glossary covers the 25 most important quantity surveying terms across four domains: measurement standards (NRM1, NRM2, NRM3, BoQ), cost management (Cost Plan, Cost Estimate, EVM, Contingency), contract law (JCT, NEC, FIDIC, EOT, Liquidated Damages), and professional bodies (RICS, Ofqual, SEG Awards). Mastering these terms is essential for study, practice, and the RICS APC.
The Royal Institution of Chartered Surveyors (RICS) publishes the New Rules of Measurement suite – NRM1, NRM2 and NRM3 – which form the backbone of UK measurement practice. These sit alongside contract suites such as JCT and NEC4, which between them govern the majority of UK construction procurement. Understanding the correct vocabulary helps surveyors communicate precisely with clients, contractors, and the legal profession.
The learndirect Quantity Surveying Online Degree Pathway (SEG Awards Level 4 Diploma, Ofqual ref 610/2941/5, and Level 5 Diploma, Ofqual ref 610/2942/7) introduces all 25 terms across the 12-unit curriculum. This glossary is the definitive reference companion for every stage of your studies.
By the learndirect Editorial Team · Last reviewed June 2025
The 25 Essential Quantity Surveying Terms
Each term below includes a plain-English definition and the context in which it is most commonly used – from pre-contract cost planning through to post-contract final account settlement. Terms are grouped alphabetically within theme for quick reference.
| Term | Definition | When used |
|---|---|---|
| Bill of Quantities (BoQ) | A structured, itemised document listing all the materials, labour and works required to complete a construction project, measured in accordance with NRM2. It is the primary pricing document sent to tenderers. | Pre-contract tender stage; also used as the basis for interim valuations post-contract. |
| NRM1 | RICS New Rules of Measurement 1: Order of Cost Estimating and Cost Planning for Capital Building Works. Provides the rules for preparing early-stage cost estimates at RIBA Stages 0–2 before detailed design. | Feasibility and concept design stages; used by client QS teams and cost consultants. |
| NRM2 | RICS New Rules of Measurement 2: Detailed Measurement for Building Works. Replaced SMM7 in 2013. Sets out 38 work sections and the rules for measuring and describing building works in a BoQ. | Pre-tender BoQ preparation; mandatory on most UK public sector projects. See the full NRM2 Measurement Guide. |
| NRM3 | RICS New Rules of Measurement 3: Order of Cost Estimating and Cost Planning for Building Maintenance Works. Applies NRM principles specifically to maintenance, repair and refurbishment scenarios. | Asset management, FM projects, and planned maintenance programmes on existing buildings. |
| JCT Contract | The Joint Contracts Tribunal suite of standard-form building contracts, first published in 1931. JCT contracts are used on approximately 70% of UK private-sector building projects. Key forms include SBC/Q, IC, MW and DB. | Private sector new-build, commercial, residential and refurbishment projects. See also the JCT vs NEC comparison. |
| NEC Contract | The New Engineering Contract suite (currently NEC4, published 2017 by the Institution of Civil Engineers). A project-management-oriented contract that uses early warning notices, risk registers and compensation events instead of traditional adversarial mechanisms. | UK public sector infrastructure, Highways England, Network Rail, HS2 and international civil engineering projects. |
| FIDIC | The Fédération Internationale des Ingénieurs-Conseils suite of international contracts. The Rainbow Suite (Red, Yellow, Silver, Gold Books) is used on World Bank, ADB and major international infrastructure projects. | Cross-border and developing-world infrastructure projects; also energy and process plant. |
| MEP | Mechanical, Electrical and Public Health – the services element of a building. MEP typically accounts for 25–40% of total construction cost on commercial and healthcare projects and requires specialist measurement rules. | Cost planning, BoQ preparation, specialist sub-contractor procurement, and NRM2 Sections 33–38. |
| BIM (Building Information Modelling) | A digital process for creating and managing information about a built asset across its lifecycle. BIM Level 2 (ISO 19650) is mandatory on UK government projects above threshold. 5D BIM adds cost data to the 3D model, enabling automated quantity take-off. | Modern QS workflows; particularly relevant to measurement, clash detection, and whole-life cost modelling. |
| COBRA | Construction and Building Research Conference – an annual international peer-reviewed conference for QS, construction economics, and project management research. Frequently cited in academic literature for cost benchmarking data. | Academic research, continuing professional development, and dissertation references. |
| Cost Plan | A structured, elemental breakdown of the estimated construction cost at a given RIBA stage. Prepared in accordance with NRM1, the cost plan evolves from a strategic cost estimate at RIBA Stage 0 to a detailed elemental cost plan at Stage 3. | Pre-contract design stages; the primary cost control tool for the client's QS team. |
| Cost Estimate | An approximate calculation of likely project cost, produced at early design stages before full information is available. May be based on floor area rates (£/m²), elemental analysis, or functional unit costs (e.g. £ per bed for hospitals). | Feasibility and RIBA Stages 0–1; used by developers and funders to test project viability. |
| Cost Engineering | The discipline of applying engineering principles to cost and schedule management – typically including parametric estimating, risk quantification, earned value analysis (EVA/EVM), and value engineering. Widely used in process plant, oil and gas, and major infrastructure. | Major capital projects, infrastructure, and manufacturing plant. Taught alongside QS in some degree programmes. |
| Final Account | The definitive financial settlement of a construction contract, agreed between employer and contractor after practical completion. Includes the adjusted contract sum plus all agreed variations, loss and expense claims, fluctuations, and contra charges. | Post-contract; typically prepared within 3–6 months of practical completion in accordance with the contract conditions. |
| Variation Order | A formal instruction issued by the contract administrator to change the scope, specification, or sequence of works under an existing contract. Under JCT, this is a “Variation”; under NEC4, it is a “Compensation Event.” Both alter the contract sum and, potentially, the completion date. | Throughout the construction phase; QS responsibility to value, agree and record all variations. |
| Contingency | A sum of money held in reserve within the project budget to cover unforeseen costs and estimating uncertainty. Design contingency (typically 5–15%) covers incomplete design; construction contingency (typically 3–10%) covers site risk. Under NRM1, contingency is a defined line item. | Pre-contract cost plan and post-contract budget management. See the full guide to construction cost management. |
| Provisional Sum | An allowance included in a BoQ for work that cannot be fully designed or specified at tender stage. Under NRM2, provisional sums may be “defined” (contractor must programme for them) or “undefined” (contract programme is not affected until instruction is issued). | BoQ preparation and tender documentation; expended via formal instruction post-contract. |
| Prime Cost (PC) Sum | A sum of money in a BoQ or specification that is reserved for the supply of materials, goods or specialist work by a nominated supplier or sub-contractor, the final value of which is not known at tender. Under modern NRM2 practice, PC sums are now less common than provisional sums. | BoQ and specification writing; adjusted to actual cost in the final account. |
| Retention | A percentage of each interim payment (typically 3–5%) withheld by the employer as security against defective work. Half is released at practical completion; the remainder at the end of the defects liability period (typically 12 months). Retention reform has been under active government consultation since 2023. | Post-contract payment applications and cash flow planning. |
| Liquidated Damages (LDs) | A pre-agreed sum specified in the contract that the contractor pays the employer for each day or week of culpable delay past the completion date. LDs must represent a genuine pre-estimate of loss (not a penalty) to be enforceable under English law following the Supreme Court ruling in Cavendish Square [2015]. | Contract drafting and post-contract delay management. |
| Bonds | Financial guarantees provided by a surety (typically a bank or insurance company) on behalf of the contractor. Common types include performance bonds (typically 10% of contract sum), advance payment bonds, and retention bonds. Required by many public sector and PFI/PPP clients. | Contract procurement and risk management; the QS advises the employer on bond requirements. |
| Extension of Time (EOT) | A formal extension to the contractual completion date granted by the contract administrator to the contractor following a qualifying delay event (relevant event under JCT; compensation event under NEC4). An EOT relieves the contractor of liability for liquidated damages for the extended period. | Post-contract delay and disruption claims management. |
| Loss and Expense | Under JCT contracts, the mechanism by which a contractor recovers costs (direct loss and/or expense) resulting from a relevant matter – for example, architect's instructions, postponement, or failure to give access. The monetary counterpart to an EOT. Under NEC4, the equivalent is the financial element of a compensation event. | Claims preparation and valuation during the post-contract phase. |
| Pain/Gain Share | A cost-reimbursable incentive mechanism, most commonly used under NEC4 Option C (Target Cost with Activity Schedule) and Option D (Target Cost with BoQ). If the outturn cost is below the target, the saving (gain) is shared between employer and contractor in an agreed ratio. If cost exceeds target, the overspend (pain) is shared similarly, up to the pain cap. | Alliance contracts, NEC Option C/D, and PFI cost reimbursable arrangements. |
| Target Cost Contract | A hybrid contract form that combines an open-book cost-reimbursable mechanism with a target price and pain/gain share. The target is adjusted for compensation events and scope changes. Widely used on complex public infrastructure projects where design scope is not fully defined at contract award. | Major infrastructure, frameworks, and collaborative procurement under NEC4 Options C and D. |
The 8 Most Important Terms – By Category
If you are new to quantity surveying, start with these eight terms – four from the measurement world and four from the contracts world. Together they form the vocabulary of daily QS practice in any UK office or site.
- Bill of Quantities (BoQ) – the pricing document at the heart of competitive tendering. Without a BoQ, tenders cannot be compared on a like-for-like basis. Prepared to NRM2 rules.
- NRM2 – the RICS measurement bible. Knowing the 38 work sections and their unit-of-measure rules is the single most important skill for a junior QS preparing take-offs. Read the full NRM2 guide.
- Cost Plan – the document the client uses to control the budget. Every design decision has a cost implication; the QS tracks those implications through the NRM1 elemental cost plan from feasibility to tender.
- Provisional Sum – the safety valve in a BoQ. Understanding the difference between defined and undefined provisional sums avoids disputes about programme obligations when those sums are instructed mid-construction.
- JCT SBC/Q – Standard Building Contract with Quantities. The most widely used JCT form on medium-to-large UK building projects. A detailed understanding of its payment, variation and termination clauses is essential for any commercial QS. JCT forms explained (Sypro).
- Compensation Event (NEC) – NEC4's catch-all mechanism for changing the prices and/or completion date. Contractors must notify a compensation event within 8 weeks of becoming aware. Missing that time bar forfeits the right to additional money or time. Compare in detail at JCT vs NEC contracts.
- Liquidated Damages – the daily or weekly sum the contractor pays for late completion. A QS must know how to calculate an LD rate that represents a genuine pre-estimate of loss; an unenforceable penalty clause leaves the employer without effective remedy.
- Final Account – the financial finish line of every contract. Preparing and agreeing the final account is one of the most commercially significant tasks a QS performs; errors here can cost clients or contractors tens of thousands of pounds.
All 25 terms in this glossary are taught across the 12-unit curriculum of the learndirect QS Online Degree Pathway. Units covering measurement (Measurement 1 & 2, based on NRM2) and contract management (Contract Practice 1 & 2, covering JCT and NEC4) are included in the SEG Awards Level 4 and Level 5 Diplomas. To understand how these terms connect to your career progression, see how to become a quantity surveyor.
Regulatory and Professional Bodies in QS – Who Does What
The quantity surveying profession in the UK is governed by a specific set of bodies. Each has a distinct role – from publishing measurement standards and regulating qualifications to awarding chartered status and benchmarking construction costs. Understanding who does what prevents confusion when reading professional literature or course marketing materials.
RICS – Royal Institution of Chartered Surveyors
Founded in 1868, RICS is the global professional body for property, land and construction. It publishes the NRM suite (NRM1, NRM2, NRM3), sets the RICS APC competency framework, and awards MRICS (Member) and FRICS (Fellow) status. RICS currently has over 134,000 qualified members globally across 146 countries. Membership is the gold standard for QS career progression and the prerequisite for most senior roles.
Standards published: NRM1, NRM2, NRM3, BCIS, PFI guidance, Whole Life Costing
Ofqual – Office of Qualifications and Examinations Regulation
Ofqual is the independent regulator of qualifications, exams and assessments in England. It maintains the Regulated Qualifications Framework (RQF) and the Register of Regulated Qualifications. All Ofqual-regulated qualifications carry an official reference number. The learndirect Level 4 Diploma in Quantity Surveying carries Ofqual reference 610/2941/5; the Level 5 Diploma carries 610/2942/7. Ofqual regulation confirms that a qualification meets nationally standardised content and assessment rigour.
Framework: RQF Levels 1–8 · Regulated qualifications are employer- and university-recognised
SEG Awards – Skills and Education Group Awards
SEG Awards (Skills and Education Group Awards) is an Ofqual-regulated awarding organisation that develops vocational and professional qualifications. They are the awarding body for the learndirect Level 4 and Level 5 Diplomas in Quantity Surveying. SEG Awards qualifications sit on the Ofqual RQF and are designed in consultation with industry. Because SEG Awards is Ofqual-regulated, the diplomas are recognised by De Montfort University (DMU) for entry onto the Year 3 BSc (Hons) Quantity Surveying top-up programme.
Awarding body for: Level 4 QS Diploma (610/2941/5) · Level 5 QS Diploma (610/2942/7)
DMU – De Montfort University
De Montfort University (DMU) in Leicester offers the BSc (Hons) Quantity Surveying degree, which includes a Year 3 top-up route for holders of a Level 4+5 Diploma in Quantity Surveying. The 2025/26 UK fee for the top-up year is £9,535. Completing the DMU BSc opens the RICS APC route: with 24 months of supervised professional experience and a final APC assessment, graduates can achieve MRICS status. The all-in cost (diploma + DMU Year 3) is approximately £11,920 – significantly less than the £28,566 charged by UBE (formerly UCEM) for the equivalent BSc over 4.5 years part-time.
Top-up fee (2025/26): £9,535 · Programme: BSc (Hons) Quantity Surveying · Location: Leicester
Frequently Asked Questions – Quantity Surveying Glossary
Start Learning the Language of Quantity Surveying
The learndirect QS Diploma covers all 25 of these terms across 12 units – 100% online, no exams, from £130.85/month. Speak to our team to find out how to get started.
NRM2 Measurement Guide · JCT vs NEC Contracts · Construction Cost Management